Try a sample Project Management Professional question

1. A municipal water authority needs a pump station built. The design is complete, quantities are known, and the authority wants to limit its own cost risk as much as possible. Which contract type is BEST?

  • A. Cost plus fixed fee, because the authority would reimburse all costs and pay a set fee as the work proceeds
  • B. Firm fixed price, because the scope is well defined and the seller bears most of the cost risk
  • C. Time and material, because the contractor would be paid for the hours worked and materials used at agreed rates
  • D. Cost plus incentive fee, because the seller's fee would be adjusted by an agreed sharing ratio of cost savings
Show answer and explanation

Correct answer: B. With a clear scope and a goal to minimize buyer cost risk, firm fixed price places the cost risk mainly on the seller. Cost plus fixed fee leaves cost growth with the buyer. Time and material has open-ended cost for the buyer. Cost plus incentive fee still reimburses costs and shares only a part of any overrun.

2. The hospital IT go/no-go review is tomorrow. The imaging lead and the lab lead each need the only integration test environment for one half day, and both confirm half a day is enough. Debating the underlying needs further would consume the time available. Which conflict-resolution approach is MOST appropriate?

  • A. Withdraw from the matter and let the two leads negotiate between themselves late in the evening
  • B. Compromise by giving each lead one half-day block so both can finish testing before the review
  • C. Force the decision by granting the full day to the lead whose workstream has the earlier planned finish date
  • D. Run a long collaborative session to explore both teams' underlying interests and design a permanent shared environment
Show answer and explanation

Correct answer: B. When time is short and each party needs only part of the resource, a quick compromise gives an acceptable result for both. A lengthy collaborative redesign is a good mode generally, but the stem says time is not available. Forcing gives one lead nothing and creates resentment. Withdrawing leaves the schedule to chance and avoids the project manager's responsibility.

3. On a water authority pump-station project, two engineers repeatedly dispute who approves valve specifications. The responsibility matrix shows both engineers marked as accountable for the same deliverable. What is the MOST likely source of this conflict?

  • A. Scarce resources, because the engineers compete for the same limited pool of lab equipment and budget
  • B. Differences in personal work style, because one engineer prefers detailed reviews and the other prefers quick approvals
  • C. Technical disagreement about valve materials, because each engineer prefers a different supplier for the components
  • D. Unclear roles and accountability caused by overlapping assignments in the responsibility matrix
Show answer and explanation

Correct answer: D. The matrix shows two accountable people for one deliverable, which is a classic cause of conflict over authority; the fix is to clarify one accountable owner. Resource scarcity is not indicated in the stem. Style differences and supplier preferences may exist but are not what the evidence points to.

What the practice exams cover

PrepGrid Exam has 2,348 verified original questions: 2,348 Project Management Professional. Each full practice exam has 180 questions with a 240-minute Simulation clock, matching the published exam length. About a fifth of items are multiple-response ("Select TWO" or "Select THREE", scored all or nothing). Drag-and-drop, matching and hotspot items on the real exam are not reproduced, and the Simulation clock does not pause for breaks.

Project Management Professional topics

  • 1.1 Develop a common vision and manage conflict: vision, conflict sources, resolution modes, ground rules
  • 1.2 Lead the project team: servant/situational leadership, empowerment, team charter, Tuckman, emotional intelligence, roles, psychological safety
  • 1.3 Engage, align and manage stakeholders and their expectations: analysis, engagement plan, trust, mentoring, customer satisfaction
  • 1.4 Knowledge transfer and plan and manage communication: methods, channels, feedback, reporting, transparency
  • 2.1 Integrated plan and delivery approach: predictive/agile/hybrid selection, tailoring, complexity, estimation, data-driven decisions
  • 2.2 Scope and value-based delivery: requirements, WBS, scope baseline, backlog, MVP, benefits and value prioritization
  • 2.3 Resources and procurement: RACI, leveling/smoothing, make-or-buy, contract types, vendor evaluation, negotiation
  • 2.4 Finance and quality: budget, reserves, earned value
  • 2.5 Schedule: critical path and float
  • 2.6 Evaluate project status and manage closure: metrics, artifacts, dashboards, closure criteria, transition, lessons learned
  • 3.1 Governance and compliance: governance structure, escalation, ethics, regulatory/security/sustainability compliance
  • 3.2 Change control and impediments/issues: change control board, impact analysis, agile change, risk vs issue, removing impediments
  • 3.3 Risk management: identification, qualitative/quantitative analysis
  • 3.4 Continuous improvement, organizational change and external environment: retrospectives, OPAs, culture, adoption, AI, market and regulatory shifts

How the practice works

Choose Study mode to see the answer and explanation after each question, or Simulation mode to practise against the official exam time and see results only when you submit. Your first 10 exams are completely different from each other, then you get unlimited generated exams.

Learn the layout in PMP exam format explained or follow the study plan.

Our questions are original PMP-style practice items, not real exam questions. PMI, PMP and PMBOK are registered marks of Project Management Institute, Inc. Not affiliated with or endorsed by the Project Management Institute (PMI).